Zone: 2 Date: January 11th, 2023
| Location/ Owner | Contractor | Start Date | Duration | Manpower | Schedule | Scope |
|---|
| TATE & lYLE | KENNNEDY TANK | ONGOING | ONGOING | 11 | 5/10S | MAINTENANCE |
| MEROM | STERLING | ONGOING | ONGOING | 1 | 5/8s | MAINTENANCE |
| VERTELLUS | KENNEDY TANK | ONGOING | ONGOING | 6 | 5/8s | MAINTENANCE |
| MEROM | STERLING | MARCH 4-17 and APRIL 1-14 | 4 WEEKS | 40 | 6/10s | OUTAGE |
| WABASH VALLEY RESOURCES | TBD | 2024 | 3-4 YEARS | TBD | TBD | FERTILIZER PLANT/HYDROGEN AND CARBON CAPTURE |
| MAPLE CREEK ENERGY | TBD | 2024 | 1.5 YEARS | TBD | TBD | 660 MW GAS COMBINED CYCLE |
| MEROM | STERLING /FREITAG | NOV 1 – DEC 26th | 8 WEEKS | 125 DAYS 60 NIGHTS | 6/10s | BOILER-AIR HEATER SCRUBBER SCR |