Zone: 3 Date: January 9th, 2022
| Location | Contractor | Start Date | Duration | Manpower | Schedule | Scope |
| MADISON | ENERFAB | MARCH 26 | 8-10 WEEKS | 30 PLUS | 4-10’S | PLANTWIDE MAINTENCE |
| ROCKPORT | ENERFAB | MARCH 11 | 10 WEEKS | 40 PLUS | 6-10’S | UNIT 1 AND 2 OUTAGES |
| WARRICK-AGC | BIDDING | MARCH 4 | 3 WEEKS | 40 PLUS | 6-10’S | UNIT 3 OUTAGE |
| WARRICK-AGC | BIDDING | APRIL 1 | 3 WEEKS | 40 PLUS | 6-10’S | UNIT 1 OUTAGE |
| GIBSON | STERLING | MARCH 4 | 10 WEEKS | 30 PLUS | 6-10’S | UNIT 4 OUTAGE |
| GIBSON | STERLING | MARCH 18 | 7 WEEKS | 30 PLUS | 7-10’S | UNIT 3 OUTAGE |
| PETERSBURG | STERLING | MAY 5 | 6 WEEKS | 30 PLUS | 6-10’S | UNIT 4 OUTAGE |